Project Schedule: FDA White Oak Campus

PhaseOccupancyEmployees in PhaseTotal Employees at White Oak
Building 64 Life Sciences Laboratory I(Occupied by CDER & CDRH)October 2003103103
Office Buildings 21 & 22 (Occupied by CDER)
July 2005
1,7131,816
Building 2 Central Shared UseSeptember 2006531,869
Building 62 Engineering & Physics Laboratory (Occupied by CDRH)March 20071942,063
Office Building 51 (Occupied by CDER )January 20089052,968
Office Building 1 (Occupied by OC)November 20081743,142
Office Building 66 (Occupied by CDRH)May 20091,3264,468
Office Buildings 31 & 32 (Occupied by OC and ORA)April 20101,0145,482
Child Care CenterJanuary 2012225,504
Office Building 71 (Occupied by CBER)April 20149986,502
Office Building 75 (Occupied by CDER and CTP)April 20141,1107,612
Buildings 52 & 72 Life Sciences Laboratories II and III (Occupied by CBER & CDER)July 20145358,147
Office Building 25 (To be occupied by OC and others) planned2021*6008,747
Office Building 45 (To be occupied by OC) planned2021*1158,862
Communications Facility, Fitness Center2021*278,889

*Assumes future Congressional funding.